Had a walk through the house Friday morning with the site supervisor, while I was there our plumber was talking to the site supervisor and said that some of our electricals got stolen, so we're going to have a camera installed :( which means no more walking inside.. & then just as I was leaving he told another worker he's waiting on our doors to be delivered, our lock up doors & sliding door cavities got stolen too ! Grr!
He also said our bricks won't be started until Thursday, but he was nice enough to stack a few for us so we could have a little bit of an idea what they'll look like, they look okay now! :)
Our plaster arrived Friday or Saturday!
& insulation was started
Looking through the dining room into the 3rd and 4th bedroom |
Looking through the kitchen into the 2nd bedroom |
Sitting/Theatre room |
Main Bedroom, Ensuite and WIR |
Family room |
& our roof architraves were delivered too..
So there probably won't be another update till Thursday..